Floor Plans and Construction Timeline
View the floor plans and illustration or view the floor plans in PDF
Timeline
Nov. 29, 2001 – Approval of Project Initiation Request of Academic Planning Committee
Jan. 16, 2002 – Draft Program Statement reviewed by the Aesthetic Review Committee
Mar. 1, 2006 – Student referendum approving funding of 50% of project costs
Aug. 1, 2006 – Revision of draft Program Statement
Sept. 11, 2006 – Project Review Board approves Program Statement
Oct. 3, 2006 – Program Statement to UNCA
Nov. 3, 2006 – Board of Regents approves Program Statement
Nov. 6, 2006 – Begin architect selection
March 2007 – Board of Regents approves architect selection
v
March 2007 – Start design
March 2008 – Complete design
May 2008 – Bid project
June 2008 – Start construction
December 2009 – Complete construction
February 2010 – Open building